Subject: SLN Airfield Construction Update 9-23-05
SLN Airfield Construction Update 9-23-05
$Account.OrganizationName
Airfield Construction Update for the Salina Municipal Airport
Runway 18/36 Now Open
Salina Airport Authority Advises SLN

Salina, Kan. September 23, 2005 Airfield construction at the Salina Municipal Airport continues on schedule. Today, Runway 18/36 along with Taxiway Echo east of Runway 18 has reopened.

Runways 12-30 and 4-22 and Taxiway B west of Runway 17/35 will remain closed through the remainder of the project.

All airfield construction is scheduled to be completed by November 15, 2005.

As a reminder, contact Wichita AFSS (1.800.262.0049) for all current NOTAMS and check the SLN ATIS (120.15)for additional information.

We will update you as new information and scheduling changes become available. Stay tuned to your email. Please feel free to forward the information to the appropriate individuals within your organization.

Rwy. 12-30 Project Scope

SAA

Salina Airport Authority
Tim Rogers, A.A.E.
Executive Director
phone: 785.827.3914

Ryan Rocha

Salina Airport Authority - Operations Manager
phone: 785.827.3914

Quick Links...

  • Salina Airport Authority
  • City of Salina
  • Salina Area Chamber of Commerce

  • Forward email

    This email was sent to shellis@salair.org, by shellis@salair.org
    Powered by

    Salina Airport Authority | 3237 Arnold Ave. | Salina | KS | 67401