Salina Airport Authority Advises
Salina, Kan.
September 8, 2005
The late summer airfield construction project at the
Salina Municipal Airport is progressing according to
schedule. The base material for the realignment of
Taxiway Bravo east of Runway 12-30 is now in
place.
Additionally, the removal of pavement between
Runway 35 and the new Threshold of Runway 30 is
well underway.
The following closures are still in effect:
- Runway 18-36 and Taxiway E remain closed. The
closures are expected to last until Tuesday, Sept.
20, 2005
- Runways 12-30 and 4-22 and Taxiway B will
remain closed through the remainder of the project.
All airfield construction is scheduled to be
completed by November 15, 2005.
As a reminder, contact Wichita AFSS
(1.800.262.0049) for all current
NOTAMS and check the SLN ATIS (120.15)for
additional information.
We will update you as new information and
scheduling changes become available. Stay
tuned to your email. Please feel free to forward the
information to the appropriate individuals within your
organization.
Rwy. 12-30
Project Scope
|
Salina Airport Authority
Tim Rogers, A.A.E.
Executive Director
phone:
785.827.3914
Shelli Swanson
Salina Airport Authority - Operations Manager
phone:
785.827.3914
Quick Links...
Salina Airport Authority
City of Salina
Salina Area Chamber of Commerce
|